The South Tahoe Greenway - Upper Truckee Bridge at Johnson Meadow Project will build upon the overall South Tahoe Greenway shared use path network through the south shore of Lake Tahoe. The Project aims to construct approximately 1.2 miles of a Class 1 shared use path and replacing a heavily trafficked bridge over the Upper Truckee River damaged by the 2017 winter storms. The Project will provide active transportation users a critical link to Barton Hospital from the west and the Tahoe Sierra neighborhood and the Lake Tahoe Community College to the east.

Planning/Design
2020
2025
2027
$9,153,626

Donaldo Palaroan (donaldo.palaroan@edcgov.us)
03/19/2019
02/07/2024
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes

Organizations

EIP Details

EIP Basics

03.02.02.0085 - South Tahoe Greenway - Upper Truckee Bridge at Johnson Meadow

This project is on the EIP 5-year list.

Transportation Details

Transportation Basics

Transportation Basics
Yes
Capital

Estimated Budgets

Estimated Budgets
/ Cost Type Total 2027 2026 2025 2024 2023 2022 2021 2020 2019
AQ Mitigation Funds (TRPA) $95,780
Preliminary Engineering $95,780 $0 $0 $0 $0 $64,780 $0 $31,000 $0 $0
Right of Way (aka Land Acquisition) $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Surface Transportation Block Grant (STBG) - California (FHWA) $769,000
Preliminary Engineering $769,000 $0 $0 $0 $0 $500,000 $0 $269,000 $0 $0
Right of Way (aka Land Acquisition) $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Grand Total $864,780 $0 $0 $0 $0 $564,780 $0 $300,000 $0 $0

Performance Measures

Expected Performance Measures

Expected Performance Measures
Miles of Pedestrian and Bicycle Routes Improved or Constructed None miles
Miles of Pedestrian and Bicycle Routes Improved or Constructed [Action Performed: Constructed], [Path or Route Type: Class I/Shared Use Path] 0.1 miles
Miles of Trails Developed or Improved [Action Performed: Improved] 0.1 miles

Reported Performance Measures

Reported Performance Measures

Reported Performance Measure Accomplishments are not relevant for projects in the Planning/Design stage.

Funding

Expected Funding

Expected Funding
$9,153,626
$864,780
$8,288,846
($8,288,846 identified as )

Total
AQ Mitigation Funds (TRPA) $771,126 $95,780 $675,346
California Active Transportation Program (ATP) Funds - Federalized (Caltrans) $6,113,500 $0 $6,113,500
Congestion Mitigation and Air Quality Program (CMAQ) (FHWA) $1,000,000 $0 $1,000,000
Surface Transportation Block Grant (STBG) - California (FHWA) $1,269,000 $769,000 $500,000
Grand Total $9,153,626 $864,780 $8,288,846

Reported Expenditures

Reported Expenditures
Total 2024 2023 2022 2021 2020
AQ Mitigation Funds $32,928 $0 $8,934 $16,168 $7,826 $0
Surface Transportation Block Grant (STBG) - Califo... $254,153 $0 $68,959 $124,791 $60,403 $0
Grand Total $287,081 $0 $77,893 $140,959 $68,229 $0

Photos

Photos

Other Details

Watersheds

No watersheds set for this project.

Threshold Categories

  • This project will preserve and enhance high quality recreational experiences by connecting major town centers with recreational opportunities from the Y, 4th Street/Barton, Golden Bear and Sierra Tract neighborhoods. This project also aligns with South Tahoe's greenway, connecting Sierra Tract to Barton.

Local and Regional Plans

Related Projects

External Links

Notes

Notes
01/23/2023 3:39 PM Judy Weber EDC completed a draft feasibility study. Anticipated completion of environmental documents Fall 2023. See the Links and Plans page for the Project Webpage link.

01/31/2019 2:53 PM Mollie Hurt Exact bridge location to be determined. Previous bridge is still standing, but does not need to be final destination for new bridge based on hydrology, geotech surveys and future restoration of the middle reaches of the Upper Truckee River. All property owners in the surrounding area need to be involved to identify final location.