| Location Information | Location Notes |
|---|---|
|
|
|
| American Recovery and Reinvestment Act (ARRA) | None | |||
| California State Water Resources Control Board (SWRCB) | None | |||
| California Tahoe Conservancy (CTC) | Whitney Brennan - California Tahoe Conservancy (CTC) | |||
| City of South Lake Tahoe (CSLT) | Stephen Anderjack - City of South Lake Tahoe (CSLT) | |||
| Tahoe Regional Planning Agency (TRPA) | Kat McIntyre - Tahoe Regional Planning Agency (TRPA) | |||
| U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) | Brian Garrett - U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) |
This project is on the EIP 5-year list.
| Miles of Roads Decommissioned or Retrofitted | [Property Ownership: City of South Lake Tahoe], [Road Type: Paved], [Treatment Type: Retrofitted] | 2 | miles |
| Linear Feet of Stream Channel Restored or Enhanced | [Action Performed: Restored], [Watershed: Bijou Park] | 500 | linear feet |
| Impervious Coverage Retired | [Land Capability of Coverage Retired: 7], [Type of Coverage Retired: Existing] | 10000 | square feet |
| Acres of SEZ Restored or Enhanced | [Action Performed: Restored] | 2 | acres |
| Acres of Environmentally Sensitive Land Acquired | [Acres of Environmentally Sensitive Land Acquired: General] | 2 | acres |
No annual performance measure accomplishments entered for this project.
| No accomplishments to report for: | |
| Year(s) | 2025 |
|---|---|
| Explanation | Project accomplishments are reported in the subproject EIP updates |
| Total | |||
|---|---|---|---|
| American Recovery and Reinvestment Act (ARRA) | $656,200 | $656,200 | $0 |
| City of South Lake Tahoe General Fund (CSLT) | $605,343 | $215,343 | $390,000 |
| Lake Tahoe Restoration Act (USFS - LTBMU) | $7,060,000 | $1,750,000 | $5,310,000 |
| Proposition 1 (CTC) | $489,752 | $489,752 | $0 |
| Proposition 1 (SWRCB) | $438,884 | $438,884 | $0 |
| SEZ Mitigation Funds (TRPA) | $189,374 | $189,374 | $0 |
| WQ Mitigation Funds (TRPA) | $210,626 | $210,626 | $0 |
| Grand Total | $9,650,179 | $3,950,179 | $5,700,000 |
| Total | 2025 | 2024 | 2023 | 2022 | 2021 | 2020 | 2019 | 2018 | 2017 | 2016 | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| American Recovery and Reinvestment Act | $503,123 | $449,350 | $53,773 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| City of South Lake Tahoe General Fund | $151,613 | $0 | $123,863 | $0 | $0 | $0 | $27,750 | $0 | $0 | $0 | $0 |
| Lake Tahoe Restoration Act | $1,750,000 | $1,295,410 | $191,089 | $93,337 | $170,164 | $0 | $0 | $0 | $0 | $0 | $0 |
| Proposition 1 | $461,977 | $0 | $0 | $0 | $0 | $0 | $455,445 | $6,532 | $0 | $0 | $0 |
| Proposition 1 | $441,741 | $0 | $0 | $0 | $0 | $23,305 | $282,473 | $135,963 | $0 | $0 | $0 |
| SEZ Mitigation Funds | $179,082 | $179,082 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| WQ Mitigation Funds | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
| Grand Total | $3,487,536 | $1,923,842 | $368,725 | $93,337 | $170,164 | $23,305 | $765,668 | $142,495 | $0 | $0 | $0 |
No watersheds set for this project.
01.01.01.0184 - Upper Bijou Park Creek Restoration Project is associated with following groups of projects.
| 01/15/2026 4:25 PM | Brianna Greenlaw | As part of LTRA FY27, requested $1.8M for Ski Run Diversion (Priority 3), $300,000 for Shirley to Whole Foods (Priority 3). Needle Peak Localized Treatment ($350,000) was tentatively funded as part of LTRA FY26 so that was removed from the list. | ||
| 01/15/2026 4:18 PM | Brianna Greenlaw | LTRA ask for FY26 includes "Upper Bijou Park Creek Phase 3e: 1) Ski Run Diversion ($1,800,000), 2) Needle Peak Localized Treatment ($280,000), 3) Shirley to Whole Foods ($230,000) for a total of $2,310,000. The TWIG LTRA ask for FY26 includes "Upper Bijou Park Creek Watershed Restoration Project (UBPC) Phase 3c - Osgood Basin Expansion ($300,000 for planning and $2,700,000 for implementation) for a total ask of $3,000,000. Adding both of these together results in the $5,310,000 request from LTRA included in the Financials. The Rockwood to Blackwood portion of the project was awarded to the low bidder and is anticipated to begin construction in May 2025. The remainder of the projects are finalizing design and are awaiting funding for implementation. |
||
| 01/11/2022 4:40 PM | Jason Burke | This project incorporates Osgood Basin Expansion (EIP #01.01.01.0156). | ||
| 01/22/2021 8:45 AM | Beth Vollmer | This project will address the watershed above the (lower) Bijou Park Creek Watershed and Restoration Project (EIP #01.01.01.0153). |