Location Information | Location Notes |
---|---|
|
California Tahoe Conservancy (CTC) | Whitney Brennan - California Tahoe Conservancy (CTC) | |||
Tahoe Fund (Tahoe Fund) | Amy Berry - Tahoe Fund (Tahoe Fund) | |||
Tahoe Regional Planning Agency (TRPA) | Kat McIntyre - Tahoe Regional Planning Agency (TRPA) | |||
Tahoe Resource Conservation District (Tahoe RCD) | Mollie Hurt - Tahoe Resource Conservation District (Tahoe RCD) | |||
U.S. Fish and Wildlife Service (USFWS) | Roy Ulibarri - U.S. Fish and Wildlife Service (USFWS) |
This project is on the EIP 5-year list.
Acres of Habitat Restored or Enhanced | None | acres | |
Acres Treated for Invasive Species | None | acres | |
Acres of Invasive Species Inventoried | None | acres |
Reported Performance Measure Accomplishments are not relevant for projects in the Planning/Design stage.
Total | |||
---|---|---|---|
California Tahoe Conservancy (CTC) | $15,000 | $15,000 | $0 |
Lake Tahoe Restoration Act (USFWS) | $1,078,250 | $278,250 | $800,000 |
Tahoe Fund (Tahoe Fund) | $3,400 | $3,400 | $0 |
Grand Total | $1,096,650 | $296,650 | $800,000 |
Total | 2024 | 2023 | 2022 | 2021 | 2020 | 2019 | 2018 | 2017 | 2016 | 2015 | |
---|---|---|---|---|---|---|---|---|---|---|---|
California Tahoe Conservancy | $15,000 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $0 | $15,000 |
Lake Tahoe Restoration Act | $20,000 | $0 | $0 | $20,000 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
Tahoe Fund | $3,750 | $0 | $0 | $0 | $0 | $0 | $0 | $200 | $200 | $1,850 | $1,500 |
Grand Total | $38,750 | $0 | $0 | $20,000 | $0 | $0 | $0 | $200 | $200 | $1,850 | $16,500 |
No watersheds set for this project.
01.03.01.0014 - Ski Run Marina Aquatic Invasive Plant Control is associated with following groups of projects.
No external links entered.
01/23/2024 7:32 AM | Dennis Zabaglo | AIS Program partners continue to strategize a treatment plan. | ||
01/26/2023 10:38 AM | Dennis Zabaglo | Planning for treatment continues to occur with program partners. Treatments will complement the Laminar Flow Aeration system. In 2022, expenditures covered site visits to assess existing plant conditions, water levels, and light transmissivity, the later information needed to understand future UV light implementation. |