Location Information | Location Notes |
---|---|
|
California Tahoe Conservancy (CTC) | Whitney Brennan - California Tahoe Conservancy (CTC) | |||
El Dorado County, CA (ELDO) | Donaldo Palaroan - El Dorado County, CA (ELDO) | |||
Tahoe Regional Planning Agency (TRPA) | Kat McIntyre - Tahoe Regional Planning Agency (TRPA) | |||
U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) | Brian Garrett - U.S. Forest Service - Lake Tahoe Basin Management Unit (USFS - LTBMU) |
Miles of Roads Decommissioned or Retrofitted | None | miles |
Miles of Roads Decommissioned or Retrofitted | |||||||
---|---|---|---|---|---|---|---|
|
2018 | 2020 | 2021 | Total | Units | ||
Property Ownership | Road Type | Treatment Type | |||||
El Dorado County | Paved | Retrofitted | 5.1 | 5.1 | miles | ||
Total | 5.1 | 0 | 0 | 5.1 | miles |
Miles of Street Sweeping | ||||||
---|---|---|---|---|---|---|
|
2018 | 2020 | 2021 | Total | Units | |
Equipment Type | Property Ownership | |||||
High-Efficiency Vacuum-Assisted Dry Sweeper | El Dorado County | 6.1 | 6.1 | miles | ||
Total | 6.1 | 0 | 0 | 6.1 | miles |
Acres of SEZ Restored or Enhanced | |||||
---|---|---|---|---|---|
|
2018 | 2020 | 2021 | Total | Units |
Action Performed | |||||
Restored | 0.2 | 1.4 | 1.6 | acres | |
Total | 0 | 0.2 | 1.4 | 1.6 | acres |
No accomplishments to report for: | |
Year(s) | 2019, 2022, 2023 |
---|---|
Explanation | Phase 1/2 constructed in 2018. Final phase constructed in 2021, with no additional work completed in 2022. |
Total | |||
---|---|---|---|
California Tahoe Conservancy (CTC) | $690,000 | $690,000 | $0 |
Proposition 1 (CTC) | $250,000 | $250,000 | $0 |
SEZ Mitigation Funds (TRPA) | $118,000 | $118,000 | $0 |
Southern Nevada Public Land Management Act (USFS - LTBMU) | $1,530,698 | $1,530,698 | $0 |
WQ Mitigation Funds (TRPA) | $85,000 | $85,000 | $0 |
Grand Total | $2,673,698 | $2,673,698 | $0 |
Total | 2023 | 2022 | 2021 | 2020 | 2019 | 2018 | 2017 | 2016 | 2015 | 2014 | 2013 | 2012 | 2011 | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
California Tahoe Conservancy | $662,077 | $15,000 | $3,453 | $413,259 | $3,747 | $216,789 | $9,829 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
Proposition 1 | $179,992 | $0 | $0 | $0 | $1,320 | $21,597 | $157,075 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
SEZ Mitigation Funds | $89,685 | $0 | $0 | $0 | $29,520 | $43,626 | $16,539 | $0 | $0 | $0 | $0 | $0 | $0 | $0 |
Southern Nevada Public Land Management Act | $1,550,275 | $25,000 | $40,860 | $276,086 | $2,913 | $11,809 | $792,235 | $129,140 | $228,524 | $28,855 | $4,862 | $2,091 | $1,238 | $6,662 |
WQ Mitigation Funds | $78,709 | $0 | $0 | $0 | $23,709 | $0 | $10,760 | $0 | $44,240 | $0 | $0 | $0 | $0 | $0 |
Grand Total | $2,560,738 | $40,000 | $44,313 | $689,345 | $61,209 | $293,821 | $986,438 | $129,140 | $272,764 | $28,855 | $4,862 | $2,091 | $1,238 | $6,662 |
No Related Projects set for this project.
01/18/2022 4:21 PM | Dan Kikkert | Phase 3 was completed in 2021. The final phase of this project is to reconstruct the existing parking lot. Work will include elevating the finish grade of the lot, BMPs, restroom facility, and sidewalk/paved path access to the multi use trail along Boca Raton. This phase may be split into it's own EIP project ... completion of this phase is currently funding dependent. |