Location Information | Location Notes |
---|---|
|
Nevada Tahoe Conservation District (NTCD) | Meghan Kelly - Nevada Tahoe Conservation District (NTCD) | |||
Nevada Tahoe Resource Team – Nevada Division of State Lands (NDSL) | Brent Moore - Nevada Tahoe Resource Team – Nevada Division of State Lands (NDSL) | |||
Tahoe Regional Planning Agency (TRPA) | Kat McIntyre - Tahoe Regional Planning Agency (TRPA) | |||
U.S. Bureau of Reclamation (USBOR) | None |
Linear Feet of Stream Channel Restored or Enhanced | None | 2100 | linear feet |
Acres of Habitat Restored or Enhanced | None | 5.25 | acres |
Acres of Forest Fuels Reduction Treatment | None | 5.25 | acres |
Linear Feet of Stream Channel Restored or Enhanced | ||||||
---|---|---|---|---|---|---|
|
2012 | 2015 | 2016 | Total | Units | |
Action Performed | Watershed | |||||
Restored | Third Creek | 2,100 | 2,100 | linear feet | ||
Total | 0 | 0 | 2,100 | 2,100 | linear feet |
Acres of SEZ Restored or Enhanced | |||||
---|---|---|---|---|---|
|
2012 | 2015 | 2016 | Total | Units |
Action Performed | |||||
Restored | 5.25 | 5.25 | acres | ||
Total | 0 | 0 | 5.25 | 5.25 | acres |
Acres of Habitat Restored or Enhanced | ||||||
---|---|---|---|---|---|---|
|
2012 | 2015 | 2016 | Total | Units | |
Action Performed | Habitat Type | |||||
Restored | SEZ/Wetland | 5.25 | 5.25 | acres | ||
Total | 0 | 0 | 5.25 | 5.25 | acres |
Acres Treated for Invasive Species | |||||
---|---|---|---|---|---|
|
2012 | 2015 | 2016 | Total | Units |
Invasive Species Type | |||||
Terrestrial | 5.25 | 5.25 | acres | ||
Total | 0 | 5.25 | 0 | 5.25 | acres |
Acres of Forest Fuels Reduction Treatment | ||||||||
---|---|---|---|---|---|---|---|---|
|
2012 | 2015 | 2016 | Total | Units | |||
Initial or Maintenance Treatment | Property Ownership | Treatment Type | Treatment Zone | |||||
Initial | Private | Mechanical Thinning | Urban Core | 5.25 | 5.25 | acres | ||
Total | 5.25 | 0 | 0 | 5.25 | acres |
No accomplishments to report for: | |
Year(s) | 2011, 2013, 2014 |
---|---|
Explanation | Project was in design and construction phases over several years. |
Total | |||
---|---|---|---|
SEZ Mitigation Funds (TRPA) | $53,000 | $53,000 | $0 |
Tahoe Bonds Act (NDSL) | $667,670 | $667,670 | $0 |
U.S. Bureau of Reclamation (USBOR) | $2,030,000 | $2,030,000 | $0 |
Grand Total | $2,750,670 | $2,750,670 | $0 |
Total | 2016 | 2015 | 2014 | 2013 | 2012 | 2011 | 2010 | 2009 | |
---|---|---|---|---|---|---|---|---|---|
SEZ Mitigation Funds | $48,268 | $0 | $0 | $48,268 | $0 | $0 | $0 | $0 | $0 |
Tahoe Bonds Act | $672,402 | $3,284 | $5,424 | $189,521 | $53,681 | $357,643 | $62,849 | $0 | $0 |
U.S. Bureau of Reclamation | $2,030,000 | $63,114 | $97,394 | $742,361 | $92,578 | $514,700 | $240,619 | $100,624 | $178,610 |
Grand Total | $2,750,670 | $66,398 | $102,818 | $980,150 | $146,259 | $872,343 | $303,468 | $100,624 | $178,610 |
No Local and Regional Plans set for this project.
No Related Projects set for this project.
12/06/2023 11:20 AM | Domi Fellers | The final Rosewood Creek Water Quality report was submitted to the Bureau of Reclamation on September 30, 2023. This project is complete |