Project addresses SR28 Corridor Management Plan and Transit Master Plan for East Shore and long term inter-regional transit. Mobility Hub location is yet to be determined. A protective acquisition of available public property is proposed at Southwood Blvd and Tahoe Blvd in Incline Village, Nevada. Formal site alternatives analysis follows to determine the final project site location. Washoe County and TTD will work with the community on the planning of the hub to identify and address local and regional transportation needs. Project planning, environmental analysis, permitting, and potential site demolition follows final site selection.

Planning/Design
2019
2025
2030
$8,500,000

01/03/2017
10/28/2024
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes

Organizations

EIP Details

EIP Basics

03.02.01.0021 - Tahoe Mobility Hub - Washoe County

This project is on the EIP 5-year list.

Transportation Details

Transportation Basics

Transportation Basics
Yes
Capital

Estimated Budgets

Estimated Budgets
/ Cost Type Total 2030 2029 2028 2027 2026 2025 2024 2023 2022 2021 2020 2019
FTA 5339 Bus and Bus Facility Program (FTA) $3,156,000
Preliminary Engineering $74,281 $0 $0 $0 $0 $0 $0 $0 $0 $0 $74,281 $0 $0
Right of Way (aka Land Acquisition) $1,881,719 $0 $0 $0 $0 $0 $0 $0 $0 $0 $1,881,719 $0 $0
Construction $1,200,000 $0 $0 $0 $0 $0 $0 $0 $0 $1,200,000 $0 $0 $0
Regional Transportation Commission of Washoe County (Washoe RTC) $160,000
Right of Way (aka Land Acquisition) $160,000 $0 $0 $0 $0 $0 $0 $0 $0 $160,000 $0 $0 $0
Surface Transportation Block Grant (STBG) - Nevada (FHWA) $202,350
Preliminary Engineering $202,350 $0 $0 $0 $0 $0 $0 $0 $0 $0 $202,350 $0 $0
Right of Way (aka Land Acquisition) $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
TDA-STA (Caltrans) $629,000
Preliminary Engineering $18,570 $0 $0 $0 $0 $0 $0 $0 $0 $18,570 $0 $0 $0
Right of Way (aka Land Acquisition) $310,430 $0 $0 $0 $0 $0 $0 $0 $0 $310,430 $0 $0 $0
Construction $300,000 $0 $0 $0 $0 $0 $0 $0 $0 $300,000 $0 $0 $0
TTD Interest Income (TTD) $11,000
Preliminary Engineering $11,000 $0 $0 $0 $0 $0 $0 $11,000 $0 $0 $0 $0 $0
Construction $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Grand Total $4,158,350 $0 $0 $0 $0 $0 $0 $11,000 $0 $1,989,000 $2,158,350 $0 $0

Performance Measures

Expected Performance Measures

Expected Performance Measures

No expected performance measures set for this project.

Reported Performance Measures

Reported Performance Measures

Reported Performance Measure Accomplishments are not relevant for projects in the Planning/Design stage.

Funding

Expected Funding

Expected Funding
$8,500,000
$4,158,350
$4,341,650

Total
FTA 5339 Bus and Bus Facility Program (FTA) $3,156,000 $3,156,000 $0
Regional Transportation Commission of Washoe County (Washoe RTC) $160,000 $160,000 $0
Surface Transportation Block Grant (STBG) - Nevada (FHWA) $202,350 $202,350 $0
TDA-STA (Caltrans) $629,000 $629,000 $0
TTD Interest Income (TTD) $11,000 $11,000 $0
Grand Total $4,158,350 $4,158,350 $0

Reported Expenditures

Reported Expenditures
Total 2024 2023 2022 2021 2020 2019
FTA 5339 Bus and Bus Facility Program $1,881,719 $0 $0 $1,881,719 $0 $0 $0
Regional Transportation Commission of Washoe Count... $0 $0 $0 $0 $0 $0 $0
Surface Transportation Block Grant (STBG) - Nevada $122,562 $0 $118,802 $3,760 $0 $0 $0
TDA-STA $316,881 $0 $6,253 $310,628 $0 $0 $0
TTD Interest Income $0 $0 $0 $0 $0 $0 $0
Grand Total $2,321,162 $0 $125,055 $2,196,107 $0 $0 $0

Photos

Photos

No photos available.

Other Details

Watersheds

No watersheds set for this project.

Threshold Categories

Local and Regional Plans

Related Projects

Related Projects

No Related Projects set for this project.

External Links

No external links entered.

Notes

Notes
10/09/2024 9:32 AM Judi Allen Added interest funds
12/20/2023 2:34 PM Judi Allen Project continues with the alternatives analysis and public outreach.
11/07/2023 4:05 PM Judi Allen $300K STA in 2025 received in 2022
01/03/2023 1:17 PM Judi Allen In October 2022, HDR Engineering was awarded a contract to develop a project concept and site assessment for an Incline Village Mobility Hub, to include the development of a public outreach plan. The Incline Village Mobility Committee meetings are on-going.
01/26/2021 10:39 AM Beth Vollmer Previously name Incline Village Mobility Hub
10/27/2020 10:46 AM Tara Frank The mobility hub will include a number of capital enhancements such as improved bike & storage facilities, park and ride lot(s), a transit/visitor center, and an operations facility.
10/16/2020 2:45 PM Judy Weber JW 10/16/20: Updated title from East Shore Transit Service Facility Upgrades to Incline Village Mobility Hub per Tara VM.