Overview

Basics

Basics
Open to the public in fall 2023, the Class I shared use path between West San Bernardino Ave and East San Bernardino Ave provides a connection over the Upper Truckee River and provides access to Washoe Meadows State Park, Tahoe Paradise Park, and the Meyers Elementary School in the community of Meyers. The project links the bike lane facilities along North Upper Truckee Rd from the west and Apache Ave to the east via a Class 3 (bike route) through signage along West San Bernardino Ave and East San Bernardino Ave.

Implementation
2015
2022
2024
$4,775,521

Donaldo Palaroan (donaldo.palaroan@edcgov.us)
07/16/2014
10/04/2024
To zoom, hold down the Shift key and drag a rectangle.
Location Information Location Notes

Organizations

EIP Details

EIP Basics

03.02.02.0027 - Class I Bike Path: East San Bernardino - West San Bernardino

This project is on the EIP 5-year list.

Transportation Details

Transportation Basics

Transportation Basics
Yes
Capital

Estimated Budgets

Estimated Budgets
/ Cost Type Total 2024 2023 2022 2021 2020 2019 2018 2017 2016 2015
AQ Mitigation Funds (TRPA) $220,710
Preliminary Engineering $52,019 $0 $0 $0 $0 $0 $0 $52,019 $0 $0 $0
Right of Way (aka Land Acquisition) $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Construction $168,691 $0 $168,691 $0 $0 $0 $0 $0 $0 $0 $0
California Highway Infrastructure Program (HIP) (FHWA) $702,869
Preliminary Engineering $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Right of Way (aka Land Acquisition) $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Construction $702,869 $0 $702,869 $0 $0 $0 $0 $0 $0 $0 $0
Congestion Mitigation and Air Quality Program (CMAQ) (FHWA) $1,872,645
Preliminary Engineering $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Right of Way (aka Land Acquisition) $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Construction $1,872,645 $0 $1,138,894 $0 $250,000 $483,751 $0 $0 $0 $0 $0
STIP Funds (Caltrans) $272,872
Preliminary Engineering $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Right of Way (aka Land Acquisition) $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Construction $272,872 $0 $272,872 $0 $0 $0 $0 $0 $0 $0 $0
Surface Transportation Block Grant (STBG) - California (FHWA) $1,453,525
Preliminary Engineering $453,525 $0 $0 $0 $0 $0 $0 $453,525 $0 $0 $0
Right of Way (aka Land Acquisition) $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Construction $1,000,000 $0 $0 $0 $0 $1,000,000 $0 $0 $0 $0 $0
Toll Credits (Caltrans) $252,900
Construction $252,900 $0 $190,225 $0 $0 $62,675 $0 $0 $0 $0 $0
Grand Total $4,775,521 $0 $2,473,551 $0 $250,000 $1,546,426 $0 $505,544 $0 $0 $0

Performance Measures

Expected Performance Measures

Expected Performance Measures
Miles of Pedestrian and Bicycle Routes Improved or Constructed [Action Performed: Constructed], [Path or Route Type: Class I/Shared Use Path] 0.37 miles

Reported Performance Measures

Reported Performance Measures
Miles of Pedestrian and Bicycle Routes Improved or Constructed
2023 Total Units
Action Performed Path or Route Type
Constructed Class I/Shared Use Path 0.3 0.3 miles
Total 0.3 0.3 miles

No accomplishments to report for:
Year(s) 2022
Explanation Project started in 2022, but not completed.

Funding

Expected Funding

Expected Funding
$4,775,521
$4,775,521
$0

Total
AQ Mitigation Funds (TRPA) $220,710 $220,710 $0
California Highway Infrastructure Program (HIP) (FHWA) $702,869 $702,869 $0
Congestion Mitigation and Air Quality Program (CMAQ) (FHWA) $1,872,645 $1,872,645 $0
STIP Funds (Caltrans) $272,872 $272,872 $0
Surface Transportation Block Grant (STBG) - California (FHWA) $1,453,525 $1,453,525 $0
Toll Credits (Caltrans) $252,900 $252,900 $0
Grand Total $4,775,521 $4,775,521 $0

Reported Expenditures

Reported Expenditures
Total 2024 2023 2022 2021 2020 2019 2018 2017 2016 2015
AQ Mitigation Funds $174,276 $0 $4,817 $120,578 $6,423 $24,204 $14,428 $3,826 $0 $0 $0
California Highway Infrastructure Program (HIP) $702,869 $0 $702,869 $0 $0 $0 $0 $0 $0 $0 $0
Congestion Mitigation and Air Quality Program (CMA... $488,043 $0 $488,043 $0 $0 $0 $0 $0 $0 $0 $0
STIP Funds $272,872 $0 $272,872 $0 $0 $0 $0 $0 $0 $0 $0
Surface Transportation Block Grant (STBG) - Califo... $735,743 $0 $321,219 $87,053 $143,636 $43,153 $81,885 $58,797 $0 $0 $0
Toll Credits $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Grand Total $2,373,803 $0 $1,789,820 $207,631 $150,059 $67,357 $96,313 $62,623 $0 $0 $0

Photos

Photos

Other Details

Watersheds

Threshold Categories

Local and Regional Plans

Related Projects

Related Projects

03.02.02.0027 - Class I Bike Path: East San Bernardino - West San Bernardino is associated with following groups of projects.

External Links

Notes

Notes
07/19/2022 2:24 PM Donaldo Palaroan CMAQ $1,468M transferred from Apache Ave Ped Safety & Connectivity Proj (#03.02.02.0006)
CMAQ $483k transferred from Meyers Corridor Operational Improvement Proj (#03.02.02.0026)
08/24/2021 12:38 PM Judy Weber Fully funded. Project was allocated $975,741. 2021 Mid-Cycle STIP $272,872 and CRRSAA program (HIP) $702,869
07/12/2019 9:34 AM Donaldo Palaroan Added 2019 RGP award of $250k of CMAQ construction for 20/21
05/04/2018 3:47 PM Donaldo Palaroan Removed previously awarded CMAQ, added to STBG FFY 19/20.
12/29/2017 2:44 PM Donaldo Palaroan Dec 2017, Added 17/18 budget (Preliminary Engineering and Construction) of the newly recommended award of the Surface Transportation Block Grant (STBG) Program